PROJECT: Asia and the Pacific Regional Geodetic Project 1997 (APRGP97)
| Mandate: | Resolution 7(b) of the 2nd meeting of the Permanent Committee on GIS Infrastructure for Asia and the Pacific, 30 September 1996, endorsed the joint cooperative APRGP97 as proposed by Working Group 3, Regional Geodetic Networks Working Group (GNWG). This resolution was subsequently endorsed by the 14th UN Regional Cartographic Conference for Asia and the Pacific, February 1997. |
| Coordinators: | Dr Ramesh Govind | Geoff Luton |
| Telephone: | 61-2-62014371 | 61-2-62014345 |
| Facsimile: | 61-2-62014366 | 61-2-62014366 |
| Email: | rameshgovind@auslig.gov.au | geoffluton@auslig.gov.au |
| Address: | Space Geodesy Analysis Centre
AUSLIG PO Box 2 BELCONNEN ACT 2616 AUSTRALIA |
| Outcomes: |
|
| Description: |
|
| Purpose: |
|
| Milestone | Date | |
| 1 | Second GNWG circular advising national agencies of plan for October 1997 geodetic observation campaign (GPS, SLR, DORIS, PRARE, VLBI), and in particular the 1 week GPS observation campaign commencing 0 hours UTC 12 October 1997 (GPS week 927) and the VLBI observation periods. | 15 August 1997 |
| 2 | Distribute GPS observation standards to national agencies with second circular. | 15 August 1997 |
| 3 | Notification to WPLTN, GFZ, CNES and APT of plan for October 1997 geodetic observation campaign. | 15 August 1997 |
| 4 | Request to CNES and GFZ for permission for participating national agencies to process DORIS and PRARE data. | August1997 |
| 5 | Confirmation with Shanghai Observatory on progress to collate the VLBI data. | August 1997 |
| 6 | Confirmation with NASA/GSDC on preparation for correlating the VLBI data. | August 1997 |
| 7 | Establish the number and distribution of permanent GPS sites by country and location in the region. | September 1997 |
| 8 | Establish the number and distribution of participating SLR sites in the region. | September 1997 |
| 9 | SLR, DORIS and PRARE observation campaign under the respective coordination of WPTLN, CNES and GFZ. | 1 Oct to 31 Oct 1997 |
| 10 | GPS observation campaign coordinated by AUSLIG (GPS week 927). | 12 Oct to 18 Oct 1997 |
| 11 | 1st set of 24 hour VLBI observations coordinated by Shanghai Observatory. | 13 October 1997 |
| 12 | 2nd set of 24 hour VLBI observations coordinated by Shanghai Observatory. | 27 October 1997 |
| 13 | Assemby of GPS, SLR, DORIS and PRARE data sets by AUSLIG. | November 1997 |
| 14 | Check all national data/logs supplied and terrestrial connections between instrumentation at co-located sites. | November 1997 |
| 15 | VLBI data to be forwarded from Shanghai Observatory to Goddard Space Flight Centre. | November 1997 |
| 16 | Distribution of geodetic data sets and data processing standards to national agencies. | November 1997 |
| 17 | Initial correlation of VLBI data by NASA/ Goddard Space Flight Centre (maximum of 6 sites). | December 1997 |
| 18 | Initial processing of PRARE data by GFZ. | January 1998 |
| 19 | Initial processing of DORIS data by CNES. | January 1998 |
| 20 | Individual technique processing and analysis of specific data sets by participating national agencies. | January 1998 |
| 21 | Individual technique processing and analysis of GPS, SLR, DORIS and PRARE by AUSLIG. | January 1998 |
| 22 | Individual national agency's processing results to be forwarded to AUSLIG for collation and analysis. | February 1998 |
| 23 | Presentation of initial analysis and results of independent technique solutions by participating national agencies at the 4th Permanent Committee meeting, Tehran, Republic of Iran. | February/March 1998 |
| 24 | Presentation of final analysis and results of combined/integrated solutions by participating national agencies at a Permanent Committee workshop in Canberra, Australia. | June 1998 |
The contact point for this web page is sec@pcgiap.org